Parallel work is progressing at the sites of both Units
In the bayed excavation pit of Unit 5 the following work processes are taking place in parallel: the placement of levelling concrete, installation of waterproofing and grounding mesh on the levelling concrete, and the reinforcement installation. At the end of each phase bays of the foundation slab of the nuclear island is poured using special concrete. During the most recent phase approximately 1,500 cubic meters of concrete were poured into the foundation slab.
The first tower crane has also been erected on the northern side of the excavation pit of Unit 5. The crane, with a 64-meter hook height and lifting capacity of 350 tons is the first in a series of dozens of such lifting machines. The cranes and lifting machines required for the construction of the Paks II Nuclear Power Plant are being installed according to schedule.
Meanwhile, in the area of Unit 6 soil cutters, crawler excavators, dozers and trucks are working on the construction of the 150-meter-wide, 190-meter-long, 23-meter-deep excavation pit, with more than a quarter of the approximately half a million cubic meters of soil already removed.
The works are being monitored by the Hungarian Atomic Energy Authority as part of an on-site inspection.
Other News
Concrete poured for reactor shaft at Leningrad's eighth unit
Over the next three months the first five tiers will be completed, up to nine metres in height. The...
Sites selected for Korean nuclear new build
South Korea's 11th Basic Plan - which covers 2024 to 2038 - calls for two new large nuclear power re...
Heavy water delivered for Argentina's RA-10 multipurpose reactor
The RA-10 is currently undergoing pre-commissioning testing which is designed to guarantee the safet...
What changes are needed to help rollout of advanced nuclear technologies in UK?
In January 2024, the British government launched a roadmap for reaching its ambition for the UK to h...
Comments
No comments yet. Be the first!
Leave a comment